According to INDOT, there’s been a slight change to the paving schedule for SR 933 in South Bend. The first two phases (Angela Boulevard to Douglas Road; Douglas Road to just south of Cleveland Road) are unchanged.Crews will then proceed from just north of Cleveland to the Michigan state line in the northbound right lane, before turning around and paving the southbound driving lane. Then, the left lanes will be done in the same rotation before crews pave the center turn lane.All paving on the entire corridor from Angela Boulevard to the state line is anticipated to be complete in early August.