In Jasper County, there will be overnight ramp closures on I-65 at State Road 14 (mile marker/exit 220) beginning on or after Monday, September 22.

The ramps at this interchange will close one at a time for milling operations, reopening after each has been milled. Crews will then close each ramp for resurfacing. Only one ramp will be closed at a time, and work will occur during the overnight hours of 8 p.m. to 7 a.m.

These ramp closure were originally scheduled in August but were postponed. The schedule is weather dependent and subject to change.

This is part of the pavement patching work on I-65 from mile marker 217 to 223 (between State Road 10 and State Road 114), with lane closures on I-65 during overnight hours. This project is ongoing through mid-October.

INDOT encourages drivers to allow extra time when driving through this area and follow traffic directions carefully.