The following is an update from NICTD on the South Shore Line (NICTD) Double Track NWI Project construction that is ongoing:
GARY- MILLER STATION AREA
All buildings have been demolished for the construction of the station and parking lots in Miller. New sewer work is underway in both the west and east parking lots. Parking is available but temporarily restricted while work near Miller Station progresses. Vehicular and pedestrian access from Melton Road (US 20) will be closed, the driveway from Old US 12/Dunes Hwy will remain open with some lane restrictions. Construction activities may occur on the shoulder of Old US 12/Dunes Hwy.
7th Avenue was closed between Floyd and Lake Street beginning Thursday, May 19th for sewer relocation work. Local access will be allowed between Floyd and Hamilton. The work is expected to be completed by June 30th but may run through July 19th if needed. There will be lane restrictions on Old US 12, but access to Miller Station will be maintained. Click here for detour map.
NIPSCO Contractors (ARC American) will be working on overhead electric lines on US 12 near Alabama St from June 13th through July 1st.
NIPSCO’s electric team may have periodic lane closures on Melton Road east of Lake Street throughout June for pole holds in support of INDOT US 20 Complete Streets project sewer main installations.
NICTD’s Double Track Contract 3, awarded to Hasse Construction, includes construction of the new east parking lot site (east of McDonald’s), which has been fenced. Construction of the new east lot began in March. NIPSCO is relocating utilities along Melton Rd.
INDOT’s US 20 Complete Streets Project in Gary:
This project is separate from Double Track. In Spring of 2022, INDOT began its “Complete Streets” project, which includes the reconstruction of Melton Rd east and west of Lake St. along with sidewalks and plantings. Any questions related to INDOT’s project should be directed to 855-463-6848.
PORTAGE/OGDEN DUNES STATION AREA
NIPSCO’s electrical team is expected to complete work just east of Portage/Ogden Dunes Station by Fall 2022. This work may require short-term travel lane restrictions and railroad flagging.
Installation of a new pedestrian signal is scheduled for Hillcrest Rd at Ogden Dunes Station for July 2022. Short-term lane closures at the Hillcrest Rd and US 12 intersection will be required for this work.
The Double Track project’s new Portage/Ogden Dunes South parking lot construction began in March 2022.
DUNE PARK STATION AREA
The east parking lot expansion is complete.
DUNE ACRES AREA
Installation of multiple large and small culverts began in early March at locations mostly west of Beverly Shores (one is east of Beverly Shores). Residents can expect equipment moving and vehicles entering and leaving Route 12 and side roads throughout the culvert installations. Culvert work is expected to end in July.
BEVERLY SHORES STATION AREA
Installation of multiple large and small culverts began in early March at locations mostly west of Beverly Shores (one is east of Beverly Shores). Residents can expect equipment moving and vehicles entering and leaving Route 12 and side roads throughout the culvert installations. Culvert work is expected to end in July.
Walsh/Herzog began removing the existing low-level platform and began building the two new low-level platforms at Beverly Shores Station the week of May 16. Installation of large beams for the NICTD catenary system east and west of Broadway began June 8. Track, overhead wire and fiber work will be ongoing in the general area in May and June.
On June 6th, Broadway was closed for 14 days to construct the new north track through the intersection. Following Broadway, on June 20, Kemil Road (E. State Park Boundary Road) will close for 14 days to construct the new north track through this intersection. Passenger loop bus service to Beverly Shores Station will be temporarily suspended during the closure of Broadway. Detour routes are being coordinated with the town of Beverly Shores and will be posted during these roadway closures. Central Ave is expected to close on July 5 for 14 days.
Road Closure: Broadway in Beverly Shores.Click here for details.
Road Closure: Kemil Road.Click here for details.
Road Closure: Central Avenue. Click here for details.
TOWN OF PINES AREA
NICTD owns the property just west of County Line Road north of US 12 in the Town of Pines where a brick company was formerly located. NICTD’s Construction Management firm, WSP, has a temporary construction office (trailer) at this location. Walsh/Herzog Joint Venture, the Double Track Project’s main contractor, also has various trailers onsite. The lot has been fenced by Walsh/Herzog Joint Venture. There are many vehicles coming and going from this property.
NIPSCO began replacing poles along the tracks in this area in early June.
Installation of multiple large and small culverts began in early March at locations mostly west of Beverly Shores (one is east of Beverly Shores). Residents can expect equipment moving and vehicles entering and leaving Route 12 and side roads throughout the culvert installations. Culvert work is expected to end in July.
Road Closure: US 12 / County Line Road. Click here for details.
MICHIGAN CITY – 10TH AND 11TH STREET AREA
Track construction is underway at the east end of the Double Track project in Michigan City (Michigan Blvd is eastern project limit).
The historic 11th Street station has been demolished and foundation removal is complete. The block is fenced and portions of the sidewalk are closed to allow for continuing work. Pedestrians must use the south side of 11th Street. The new north boarding platform foundation is being built as of May 2022.
Construction on 11th Street began February 28, 2022, which included a full closure of 11th St itself. Michigan City residents can expect north/south street closures that progress westward as construction advances, with signage indicating which streets will be closed and when. Residents, businesses and other property owners are also being notified of any work that will impact ingress/egress for their particular site.
Installation of the overhead catenary poles is in progress in the Right of Way south of 10th St.
Comcast will be splicing their utilities in the Tennessee and 11th street area the night of June 17th.
Additional road closure details:
On February 28, 2022, Walsh/Herzog (WH) closed 11th Street from Chicago Street to Michigan Boulevard. This closure is required to build the two new South Shore Line tracks, create an isolated railroad right-of-way, and improve public safety along 10th and 11th streets.
Pursuant to the 2016 Agreement with Michigan City, the intersection of 11th Street with the following streets will be permanently closed and configured into cul-de-sacs in accordance with the final, approved design.
– Elston Street
– Manhattan Street
– Buffalo Street
– Pine Street
– Spring Street
– Cedar Street
– York Street
– Maple Street
The intersection of 11th Street with the following streets will only be closed as required to construct the work across the intersections.
– Chicago Street
– Ohio Street
– Wabash Street
– Washington Street
– Franklin Street
– Lafayette Street
– Oak Street
It is currently anticipated that two closures of each of these intersections will be required with each closure lasting approximately two to three weeks.
To maintain traffic flow in the north south direction past 11th Street, the following constraints will be implemented by Walsh/Herzog:
Tennessee St will remain open when Ohio St is closed until the Ohio Street crossing is re-opened.
The intersections of Wabash St, Washington St, and Franklin St will only be closed one at a time.
The intersections of Lafayette St and Oak St will also only be closed one at a time.
Michigan Boulevard will remain open throughout the duration of the project.
The intersections at 11th and Franklin were converted from a stoplight to a stop sign configuration during construction. Construction on 10th Street will occur to the south of the existing roadway, where the two new tracks will be installed. At the completion of the work, the current tracks down 10th Street will be removed and the roadway repaired.
On June 6th, the intersection of Washington Street and 11th Street was closed and will remain closed for 30 days for construction of the new north track. Franklin Street and Wabash Street will remain open during the Washington Street closure to provide north-south access across 11th Street.
After completion of the Washington Street closure, Wabash Street will be closed at 11th Street to construct the new north track through this intersection. Washington is expected to close for approximately 30 days on July 5th. Road closure information will be updated as work progresses.
The City is currently working with developer Flaherty & Collins, to evaluate alternative Transit Oriented Development (TOD) options for the block bounded by 10th, 11th, Franklin and Pine Streets. Plans for that development are in progress. Questions should be directed to the City of Michigan City for the TOD effort.