NICTD gives update on South Shore Line Double Track NWI Construction
NICTD released a new construction update for NICTD’s Double Track Northwest Indiana project: Gary- Miller Station Area For the Double Track project’s new Miller parking lot, demolition of structures began the week of 12/6/2021. NICTD’s Double Track Contract 3 received a Notice to Proceed 9/9/2021 and construction is expected to begin at the east parking lot Spring of 2022. Sewer work will begin in the south portion of the existing parking lot (west of Lake St) in March 2022. Parking will be available but restricted in this lot. The access from Melton Road (US 20) may be impeded, but the driveway from